Open symbolOpen
×

Parallel Thimble Shoal Tunnel
A Project Update

Following a groundbreaking ceremony in 2017, Chesapeake Tunnel Joint Venture (CTJV), a joint venture comprised of Dragados USA and Schiavone Construction Company, LLC began work on Phase II of the CBBT’s Parallel Crossing project. This phase, known as the Parallel Thimble Shoal Tunnel Project,  will construct a two-lane tunnel under Thimble Shoal Channel.  When complete, the new tunnel will carry two lanes of traffic southbound and the existing tunnel will carry two lanes of traffic northbound.  Construction cost for this one-mile long, bored tunnel project is $755,987,318.  

What's New?

Throughout the summer and early fall, CTJV has been working on the assembly of CHESSIE, the TBM that will bore the one-mile tunnel at Thimble Shoal Channel.

In early October 2022, the assembly of CHESSIE began in the launching pit.

On November 1, 2022, the 43-foot diameter cutterhead was installed.

The first of four  back-up cars is now in place and CTJV will continue to work on the assembly of the remaining three through the holidays while work continues on the assembly of the main shield.

The GOAL:  CTJV hopes to have the TBM fully assembled in January 2023.  Once complete, Chessie must go through a series of testing procedures before the actual boring can begin, which is anticipated to start in early spring 2023.

All work on the base slabs is now complete and work continues on the retaining and fascia walls.

The second conveyor belt bridge was installed over the roadway this fall.  Like the first conveyor belt bridge, due to its enormity, this was transported northbound to One Island via the southbound trestle.  The conveyor systems will be used to move the soils that Chessie digs from the Bay bottom.

On the north side of the island, work progresses on the construction of the engineered berm.

Two Island

The demolition of the retaining wall on Two Island is complete, providing southbound travelers with a line of sight into the receiving pit.

Work continues on the build-out of the receiving pit, dock and pier as well as the engineered berm on the south end of the island.  This work will continue over the course of the next year.  Remember, much of the work on Two Island will mirror that of One Island.

Tunnel Segments

At CSI in Chesapeake, VA, more than 9,000 tunnel segments are complete and await their installation. When Chessie is ready to begin her dig, these segments will be trucked to One Island.

Explore Careers

We employ dedicated people who meet the challenge of customer service.

Employment Opportunities