Milling and Repaving Project

The milling and repaving of portions of the CBBT is set to begin in early September.  This paving project will begin at Fisherman Island and continue across “C” Trestle Southbound to Portal Island #4.

The project will result in a single lane closure across “C” trestle southbound and travelers should use caution as they travel through this work zone.  This portion of the project is anticipated to be complete in late November 2019.  Work will resume across “C” trestle northbound in the spring of 2020.

This capital project to mill and repave the trestles and replace end dams was awarded to Allan Myers of Worcester, PA and this is the first repaving project performed since the Parallel Crossing Project, Phase I was complete in 2000.